Five document errors that delay a shipment

Cargo in a temporary storage warehouse costs money every day. Almost all delays related to documents come down to five repeating situations.

Below are the situations that occur most often. All of them can be found at the preparation stage, if you know where to look.

1. The names do not match

The declaration says “household textile footwear”, the invoice says “slippers”, the marketplace card says “Slippers Cozy Home”. Formally these are three different products. A mismatch is the most frequent reason for a request for additional documents.

How to avoid it Fix one product name in all documents of the chain: the contract, the invoice, the permit document, the product card. Put the marketing name in the description.

2. A wrong HS code (TN VED)

The code determines the duty rate and the list of permit documents. If the code in the conformity document does not agree with the code in the goods declaration, the controlling authority has grounds for a check. A detailed analysis is in the article on classification.

3. The document has expired or is suspended

What to check regarding terms
Validity period of the document
up to 5 years
Status of the laboratory accreditation certificate
on the date
Inspection control
annually
Under schemes with inspection control, a document can be suspended during its validity period too — if the control is not passed.

4. Not all the regulations are covered

The product falls under two regulations, but the document is issued for only one. A classic example is electronics: TR CU 004/2011 on low-voltage equipment and TR CU 020/2011 on electromagnetic compatibility. The first was issued, the second was forgotten — the set is incomplete.

5. Labelling applied without a basis

The EAC mark on the packaging without a valid document is a violation in itself. The opposite situation is no better: the document exists, but there is no mark, although the regulation requires it. Both directions must be checked.

Checklist before shipment

Checking the contractor before concluding the contract is helped by the analysis of the Rosaccreditation register, and understanding which document is needed at all — by the article on forms of conformity confirmation.

6. The test report does not relate to your batch

The document exists, the register shows it, the scheme is batch-based — but the batch in it is a different one. This happens when the supplier issued the document once and attaches it to all later shipments.

A batch document is tied to a specific volume: the quantity, the invoice number, the details of the delivery. The next batch of the same product is not covered by it, even if it is identical. This is checked in a minute — by comparing the batch data in the register card with your shipping documents.

A separate case is when the tests were done on a sample that does not reflect serial products: a different material, a different set of parts, a pre-series unit. Formally the test report exists, but in fact it describes a different product. How to select samples so that this does not happen — in a separate article.

7. The applicant is not the one who imports and sells

The document is issued to the supplier's company, but you import and sell. The document itself is valid, but the link between it and your delivery is not confirmed by anything.

This error almost never shows up at customs, but it regularly comes up during a marketplace check and when a buyer makes a claim.

Change of factory The supplier moved production to another plant and did not say so. The range is the same, the documents are at hand, but a different manufacturer is named in them. Formally the products are left without conformity confirmation. A clause on notification of a change of site and composition should be written directly into the supply contract.

8. The labelling and the documents have diverged

The inspector does not need a laboratory to find this error: it is enough to take the packaging and open the register. There are four kinds of mismatch.

Where they divergeWhat it looks like
NameThe label says “Moisturizing children's cream”, the document says “Children's cream”
ManufacturerOne plant on the packaging, another in the document
Age or other target group“3+” on the product, the documents are issued for a younger group
Composition and characteristicsThe tag says “100% cotton”, the test report shows a different composition

The rule is simple: the text on the packaging and the text in the document must match word for word where it is about the name, the manufacturer and the characteristics. The marketing name can stand next to it, but not instead of it.

How to build a check so that errors do not repeat

All eight errors have one thing in common: they are found in a few minutes if you know where to look, and are never found if you check “by feeling”. What helps is not heroism but routine.

And the main point about terms: documents are prepared before the product is put into circulation, not after the first request. Almost every error listed is cheap at the preparation stage and expensive at the stage when the cargo stands in a warehouse or the card is blocked.

Check your product Describe your product in plain words — the system will show the expected HS code (TN VED), the applicable regulations and the set of documents. Start the check.